Automatically mark "In Progress" an issue when all its linked issues "Is Blocked By" are Done

Lakshmi CH
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 25, 2025

Hi Team,

Automatically move the Defect Issue Type ticket to "In Progress" status when all its linked issues "Is Blocked By" are Done from tickets that are related to any other issue type. I used the automation rule below, but the ticket defect's status is not changing, even though all the linked tickets are done. Did I miss anything in this automation rule?

automation rule.png

1 answer

0 votes
Trudy Claspill
Community Champion
August 25, 2025

Hello @Lakshmi CH 

Can you share with us the information you are getting in the rule Audit Log when you mark the last of a one of the "is Blocked By" linked issues to Done?

The output when you set any of the "is Blocked By" linked issues to Done, whether the first, second, or last, would also be informative to helping us debug your issue and advise you.