I am trying to create a JIRA automation Time Tool that would allow dates for a target schedule to auto populate based on a date field being entered. Would this be possible using the {{fieldChange.to}} smart value?
I've tried using, {{issue.customfield.Launch Date.minusWeeks(2)}} for the install date field in automation, but it never populates
The schedule I'm trying to set up is,
User will enter launch date
Install date will auto populate to 3 weeks before launch date
Shipping date 1 week before install date
Test date 1 week before shipping date
Order date 6 weeks before test date
Any help would be greatly appreciated!
Hi @Bill Bayer
I believe your smart values for the field may be incorrect. Please try this one for the example you noted:
{{issue.Launch Date.minusWeeks(2)}}
If that does not work, please try using the information in this how-to article to confirm the name of the smart value for your field: https://support.atlassian.com/cloud-automation/docs/find-the-smart-value-for-a-field/
Kind regards,
Bill
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.