Assigning story points at the time of story creation

Muhammad Haarris Ahmed
Contributor
July 2, 2024

When we create stories in our board, we can't add story points in right there - we have to edit afterwards. Can someone please help me find a setting to address this please, so we won't have to edit the story again to add story points? 

1 answer

2 votes
John Funk
Community Champion
July 2, 2024

Hi Muhammad,

Try adding the Story Points field to the Create screen for the project.

Muhammad Haarris Ahmed
Contributor
July 2, 2024

Thanks John.

Like John Funk likes this
John Funk
Community Champion
July 3, 2024

Did that work for you? 

Muhammad Haarris Ahmed
Contributor
July 3, 2024

I tried, but the interface to add fields to "create" button didn't show up in my system. I'm assuming it could be as I'm not the admin of the overall Jira instance in my organisation (I'm only the admin of my Jira project).

I'll be working with my org's Jira admin to see if it works. Really glad to know that there's a way around to fix it. Will definitely loop in to seek more guidance if required.

John Funk
Community Champion
July 4, 2024

Yes, a Jira Admin will be the one who needs to add that. 

Like Muhammad Haarris Ahmed likes this
Muhammad Haarris Ahmed
Contributor
July 11, 2024

Hi John, hope you are doing well. We’ve made some good progress on the above. Just wanted to share to close the loop. In short, we accessed the Field setting via project settings, updated the story points field, and added it to the Field tab of the project’s screen schemes. (I've just noticed that there are way too many 'field' in this text, lol). Thanks for the pointers, much appreciated!

Like John Funk likes this
John Funk
Community Champion
July 11, 2024

You are very welcome. 