Firstly thanks for your atention.

I'm working on a Software proyect managed by the team. In the Done columns, shows few  old task. I need to create (it it's possible) a rule that hidden task where date of done is more olded that 14 days.

1 answer

0 votes
Trudy Claspill
Community Champion
February 15, 2023

Hello @Carlos Moresco 

Welcome to the Atlassian community. 

In a Team Managed Software project Kanban board issues in the last column will automatically be hidden when the Resolved date is more than 14 days in the past.

If you are not experiencing that, please show us an image of your board that includes an issue that you think should be hidden, and show us the details/dates for that issue.