With our previous version of Jira 7.6.x we did sprint planning with Tempo Team Planner (Team - Board View I think is what it was called)
With the new version of Tempo and capacity planner it will only work if we plan every hour of every day which we don't. We only plan at a high level the 80 hours in the 2 week sprint for the scrum team at the individual level.
I am curious how are other teams are doing sprint planning around hours within Jira? I want to know based on the resource estimate how many hours they have remaining or are they over booked (from an hour perspective)? With the new version of Jira I lost this... surely somebody is doing this and have figured this out.
I found this, I assume some people are using this paid add-in