Hello -
I have created a plan view in Advanced Roadmaps where I am pulling data from 3 different boards/sources. The epics and related issues from these boards are being pulled in fine - however I want to introduce Themes and Initiatives as well.
What is the best way for me to link these existing Epics to newly created Themes and Initiatives? The hierarchy would be:
FYI - these are company managed projects. Hope my question/query makes sense.
Thank you!!
Hi @Farhad Babury and welcome to the Community! The hierarchy is based on the Parent field. Ensure that field exists on your Epics and Initiatives (Create, View and Edit) and you can then link your Epics to Initiatives and Initiatives to Themes. HTH