Hello,
I could not select all needed projects to create an advanced roadmap
Could you please tell me why ?
Thanks
Hi @Kaouther BEN KHEMIS and welcome to the Community!
Jira software supports 2 types of projects: team and company managed. You can check out this support article to learn more about the differences.
In short, company managed projects share their configuration, while team managed projects are more siloed. Advanced roadmaps only supports company managed projects to be included in a plan. Which is what you can see in the list from your screenshot.
Hope this clarifies!