I am using a Scrum project and trying to set up the timelines with the roadmap. However I cannot see the bars for the subtasks until I set up the Sprint. Is there any other way I can make the bars for subtasks visible?
Thanks.
Hi @Johnny Wong ,
If you are using premium plan of Jira Software, you can use Advanced Roadmaps in which you can set the hierarchy levels till "sub-tasks".
Thanks,
Aditya
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.