Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

A task having multiple sub-tasks and few are completed in current sprint and rest to be moved

PavanPalli
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
April 21, 2021

I have task A which has 6 subtasks all are planned in sprint 1. Now 4 sub-tasks are completed and 2 subtasks are planned to take it up in next sprint. How do i move the subtasks to next sprint?

1 answer

1 accepted

0 votes
Answer accepted
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
April 21, 2021

Sub-tasks are not sprint items themselves.  There's no such thing as "sub task in a sprint on its own".

Sub-tasks are part of a sprint when their parent issue is in it.  This is because a sub-task is part of its parent, not a separate entity.  

The 4 sub-tasks that are complete, great.  You've got two not complete, also fine.  This means the parent issue is not done.

So take task A into the next sprint to continue with it.  The 2 incomplete sub-tasks will then be part of the sprint because their parent is.

PavanPalli
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
April 21, 2021

Thanks for you response.

In this case how we calculate velocity? only 4 subtasks points to be considered?

Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
April 21, 2021

Velocity is a measure of what you commit to in a sprint vs what you achieve.

Sub-tasks are not sprint items, you don't commit to them, you commit to delivering their parents.

There's an essay on how to do sub-task estimates, but the outcome is

1. They do not directly count to velocity themselves.  If you do use estimates on sub-tasks, they only matter as part of the estimate of their parent

2. Jira does not natively have any support for any scheme for summing sub-tasks.  If you're going to do estimates on sub-tasks, you'll need to build/automate something.  Very carefully.

3.  Even if you do estimate sub-tasks, your velocity is still calculated on stories.

So, in the case you've got, you do no burndown until sprint 2, where, assuming all 6 sub-tasks are complete and then the story can be completed, you will burndown on the story estimate.

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
STANDARD
TAGS
AUG Leaders

Atlassian Community Events