I've successfully imported the board from Trello to JIRA and adjusted it as needed (int JIRA).
The team did some changes in Trello before starting usage of JIRA.
Is it possible to syncronize those changes to existing JIRA project (initially imported few days ago)?
Hello @Taras,
Welcome to the Atlassian Community!
When importing Trello to Jira, a new project will be created and it will be independent of the Trello board. If importing the same Trello board again, it will not be possible to sync with the existing one.
There is a feature request suggesting the implementation of this ability:
Please, click on vote and also watch the ticket above to receive future updates.
For now, if nothing was changed in Jira, maybe import the Trello board again to create a new project and delete the other one.
Kind regards,
Angélica
Thank you!