We have a Project that has tickets with a due date and 3 statuses(Todo, In Progress, Done). We would like to show a dashboard with these 3 states as well as a column for Out Of SLA(Due Date <= now()). Is there anyway to combine these two filters?

1 answer

1 accepted

1 vote
Answer accepted
Sriram Balasubramaniam
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
May 26, 2022

Figured it out.

I needed to create 2 filters separately.

Then create an empty dashboard. Add widgets

Add filters and choose the ones created