Accessing a Completed Sprint

Ryan Lampert August 27, 2021

Is there a way to pull up a completed sprint?  I am essentially trying to test each of the tasks/tickets on a sprint after it has been completed, and it seems my only option is to know each of the ticket numbers and pull them up individually.

1 answer

1 accepted

0 votes
Answer accepted
Jack Brickey
Community Champion
August 27, 2021

You can access previous sprint details under the reports section. Look at the sprint report.

Ryan Lampert August 30, 2021

Thank you, Jack.  Is it required to be the administrator of the project in order to access the sprint report?  I am not the administrator and am having trouble finding the sprint report.

Jack Brickey
Community Champion
August 30, 2021

Can you share an image of your project screen? It may be that you are on a TMP project. If that is the case and you don’t see reports in the sidebar then it may be that that is not turned on. For that project admin would need to go into project settings > features and turn on reports. Also for TMP projects you don’t have the “sprint report “but you do have a sprint burn down which will also achieve your goals I think.

If you were on a CMP project then reports should definitely be there and you do not need to be a project admin to see it.

Ryan Lampert August 30, 2021

Here is a screenshot of all the projects I have access to.  The boxed project is the one in question.  

Jira_Projects.png

Once I click on this specific project, here is a view of the next screen:

Jira_Projects2.png

 

Thanks for your help!

Jack Brickey
Community Champion
August 30, 2021

there should be a sidebar like below...

2021-08-30_10-40-50.jpg

Ryan Lampert August 30, 2021

Aha!  That sidebar was collapsed.  This is perfect.  Thanks so much for the help!!