I created new Jira issue. I could choose start date and due date but i couldn't chose end date of my task.
Community moderators have prevented the ability to post new answers.
Hi,
We are using Jira Gantt chart project. When we modify dates from Gantt chart (Auto-Scheduled All), it modifies the Start date / End date for tasks. But we are not able to see them in Jira. We have tried adding Planned Start Date / Planned End Date fields to Screen, but it does not display anything.
Have you put data into the fields? Jira doesn't display empty fields.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
It looks like you have not added a field for "end date". To the right hand side of your screenshot, there is a section that allows you to add fields, you can add it from there
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.