The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Relationship Between Resolution and ResolveDate

Olive Sun
Contributor
June 23, 2021

Hi There,

 

I used to think that once an issue is transited to a status in which StatusCategory = done, then the resolved date will be set. However, it seems wrong.

We have many issues in the final status but do not have a resolved date. Any thoughts?

 

Thanks,

Olive

1 answer

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Answer accepted
Joseph Chung Yin
Community Champion
June 23, 2021

@Olive Sun -

In Jira/JSM, "Resolved Date" is set when "Resolution" value is set for issues.  You need to check your project's WF for your terminal (final status) to see if there is any setup where it applies the resolution value.

In your case, I can tell those issues in the final status that their's Resolution values are empty (represented by "Unresolved").

Hope this helps.

Best, Joseph Chung Yin

Jira/JSM Functional Lead, Global Infrastructure Applications Team

Viasat Inc.

Olive Sun
Contributor
June 23, 2021

Thanks, @Joseph Chung Yin

Totally understand now!

Joseph Chung Yin
Community Champion
June 23, 2021

@Olive Sun -

Excellent.  Glad to help.  When you have a chance, please click on "Accept answer" button.

Best, Joseph