Hi Jira Community,
I am trying to export a list of issues from a filter to .csv but the Original Estimate value is mis-stated on the export file. In each case, the exported estimate is three times lower than the value on Jira.
I understand that the export returns the Original Estimate values in seconds, however even when accounting for this, the results I get are incorrect.
For example:
US1 - OE = 3 days | Export = 86,400 = 1 day
US2 - OE = 1 day | Export = 28,800 = 0.33 days
US3 - OE = 4 hours | Export = 14,400 = 0.167 days
Is this a known issue? Does anyone have a fix?
Best wishes,
James
Community moderators have prevented the ability to post new answers.
Welcome to the Atlassian Community!
Those look right to me. Jira looks at working time, not full time when you are using estimates. The defaults are 1 week = 5 days = 40 hours, but you can change that in the general configuration.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Welcome to the community. To supplement what @Nic Brough -Adaptavist- provided, here is the link on how to configure the work time - https://support.atlassian.com/jira-cloud-administration/docs/configure-time-tracking/
NOTE - The change of the default setup is applied at the GLOBAL level, so it will affect your entire JSM env's projects.
Hope this helps.
Best, Joseph Chung Yin
Jira/JSM Functional Lead, Global Infrastructure Applications Team
Viasat Inc.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks you Joseph, I appreciate you answering and providing this extra information!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.