The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Is it possible to take dates from history and put them in to the fields?

Vladimir Sumilin
Contributor
June 16, 2023

Hi everyone,

Is it possible to automatically capture the date when the status of an issue in a project changes, such as from "TO DO" to the "Planning" phase, and then store this date in a custom field?

I would like to have it for the whole path for the issue, maybe some of you guys know how to do it :) 

 

Best regards,

Vladimir 

 

1 answer

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

3 votes
Answer accepted
Roberto Miasack
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
June 16, 2023

Hi, Vladimir! How are you?!

 

Yes, it is possible. You need set a value on field that you neet copy the date. And you can do this on Automation. (I used Due date)

1.png

 

To manipulate the date with something, you can use date smart values. Like that:

2.pngHope this helped you!

Roberto Miasack 

Vladimir Sumilin
Contributor
June 19, 2023

Hello @Roberto Miasack

Thank you for your answer!

Best regards,

Vladimir