How can I set a rule that allows change transition status from in progress to done with the obligation filled issue field "customer"? Should I configure it in workflow? Which condition should I use?
Community moderators have prevented the ability to post new answers.
Welcome to community!
Yes, the requirement is possible through workflow change. You can add the field required validator. More info in https://confluence.atlassian.com/jirakb/how-to-make-a-field-required-before-closing-the-issue-1236928291.html
Thank you for the tip. It was simpler than I expected. Have a nice day :)