Hello,

At present, the order of Resolutions is the same for the whole Jira instance.

We'd like to change the order and the default of Resolutions by project (Company-managed projects only).

For instance, Project A has a default of Unresolved and shows Won't do as second choice. Project B has a default of Done and shows Unresolved as second choice.

Is that possible ?

Thank you

2 answers

1 accepted

1 vote
Answer accepted
Sharumathy Krishnan
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 7, 2024

Hi @Pierangelo Repetti 

Currently the feature to re-order the resolution based on the project level is not available. There is a ticket with Atlassian, you can watch & vote the ticket. You'll be notified if they have any feature development - https://jira.atlassian.com/browse/JSWCLOUD-24167 

But if you would like to limit the resolution based on the project, you can achieve it through the workflow properties. Kindly check out this - https://valiantys.com/en/blog/atlassian-administration/jira-workflow-limiting-resolution-field-options/ 

Hope this helps!

 

Thanks,

Sharu

Empyra Software Solutions

 

Pierangelo Repetti
Contributor
February 7, 2024

Thanks @Sharu - Empyra I see the feature has currently just one vote...no hope to see it implemented I guess. Anyway, I'll add mine.

Like # people like this
0 votes
Nikola Perisic
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
February 7, 2024

Hello @Pierangelo Repetti 

Yes, the order can be changed.

To do this:

  1. Press a dot on your keyboard and type Resolutions (much faster way)
  2. You will be presented with this screen:Screenshot 2024-02-07 at 09.42.27.png

     3. Use the arrows within the Order column to move them up and down - for example Done was first, I clicked on the down arrow and it moved down

Pierangelo Repetti
Contributor
February 7, 2024

Hi @Nikola Perisic 

that's an order valid for all the projects in our Jira. I want to change the order for just one project.

Thank you

Nikola Perisic
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
February 7, 2024

Sadly no, this cannot be changed per project, it reflects to all of the projects