CRON Schedule Jira Automation

Mar
Contributor
January 20, 2026

I created a Schedule Automation using CRON with a value of  0 */15 8-19 ? * *.

Why is still keep running even I input only run 08:00 to 19:00?

I need it to run only every 15 mins of working hours every day,

 

here is the image

Audit logs
logs.pngschedule.png

1 answer

1 accepted

5 votes
Answer accepted
Christos Markoulatos -Relational-
Community Champion
January 20, 2026

Hi @Mar 

In Jira Automation, CRON expressions are always interpreted in UTC. This often leads to rules running earlier or later than expected when viewed in local time. For example, a CRON set to run between 08:00 and 19:00 may appear to run until 21:00 or 22:00 if your site or rule is still using UTC while you’re in a different timezone. To avoid this, adjust the times in UTC so that the schedule fires at the intended local hours.
Hope this helps!