I'm working through our first use of Advanced Roadmaps/Plans and am currently looking at the Summary, which seems like it could be helpful, but I'm a bit confused about the various widgets, in particular the Team capacity one.
Right now it's saying that there are no active sprints in the backlog so it's not showing data:
I've already worked through a few issues w/ getting stuff visible on the plan, so I've set my plan's issue source to the board (instead of the project), and I've also made sure that the board is associated w/ the team (which is plan-only). The board does have sprints - some completed, one active and some future.
I've also made sure that the changes have been saved back into Jira, so I'm at a loss as to why nothing is showing up under Team Capacity on the Summary. Appreciate any help!
Solved! Go to Solution.
Community moderators have prevented the ability to post new comments.
Did a test with one active item from the current sprint and it looks like that did it, thanks!
Pretty frustrating that all these little connections are needed and not outlined anywhere :(
This was especially helpful, thank you.
Hi @Ashleigh Lodge , another thing that you can check is if your active Sprint dates overlap with the date range of Summary page dates? Although a sprint is still active, but if the sprint start & end date doesn't match with the Summary page dates, the sprint won't show up.
Hope this helps!