Automatically shift the start dates and end dates of all issues that are dependant linked

Vandana Mandal
December 5, 2025

Hello, 

Seeking help in Jira Plan. 

Let's say I have one ticket (ABC) which is blocked by another ticket-123. Since ABC release is dependent on Ticket-123, lets say the end date got changed or by any reason it got delayed. Is it possible to change the start date and end date of ticket-ABC accordingly in Jira Plan. 

If it is feasible, what are the steps?

 

Thanks

1 comment

Comment

Log in or Sign up to comment
Trudy Claspill
Community Champion
December 5, 2025

Hello @Vandana Mandal 

Are you using Jira Cloud or Jira Data Center?

If you are using Jira Cloud you might find this article I wrote helpful. It talks about how to solve the problem you mentioned using Automation Rules.

Updating dependent task's dates when predecessor task date changes 

Like Hans Polder _Devoteam_ likes this
Trudy Claspill
Community Champion
December 23, 2025

Hello @Vandana Mandal 

Were you able to address your requirement with the reference article I provided?