Hello, I'm using a company managed project in Kanban. It's been a week that I am using this projet. It was created on June 17th. I would like to have insights regarding the cycle time of the...
I love the details and insights I could get from the Control Chart as well as the CFD. I am curious if we can add a widget to allow us to show that info on the Jira Dashboard? We are tryi...
Hello, I am trying to track days issues are spent in a column. I can see dots when I look at a board view but where do I find that info in reports. The control chart seems to have what I nee...
Good Afternoon Atlassian Community/Superstars, The data from the Control Chart Report in Jira Software is so different from Time in Status add-on in Jira Software (which seems more correct) for some...
Since migrating to the cloud when we create a control chart there is no data for any of our custom status's pre-migration. The out of the box status' display fine but not the custom status'. ...
I am trying to find the following to determine whether we can use Jira Control Chart as a reliable cycle time measure: What is the formula used for calculating Average cycle time in Jira Control Ch...
I am using control chart to track data in regards to teams' delivery. Recently I'm spotting many issues that I find out are outside the scope of my query yet Jira has included them into the ca...
I have a team managed Project, when i go to reports to set up some, I cannot see the option to configure, reports are showing up in readonly mode. HOw can i add the cycle time report or control chart...
In control chart, sometimes US are clustered (group together). Is there a way to separate the display so I can see the breakdown of the cycle time for each US?
Hello, My team is working in Kanban, and I am using the Control Chart report to view the Cycle Time and analyze team performance. Stories have different weight (Story Points), however the Control C...
Anyone has any ideas what causes this---> There are either no issues on this board, or all the issues have been filtered out by the chart refinements. An error occurredHide…(18) Please try refr...
My control chart is showing an average cycle time of 2w 6d 5h (non working days unticked) but the working days are configured as monday - friday (5d). Shouldn't this show 3w 1d 5h?
Is there any bad impact or calculation error of the Control Chart cycle time when an issue returns to a previous step of the kanban board ?
Hi, Is there any way to show total average (for all filtered tasks) cycle time breakdown by stages? Control Chart Board shows this only for each task separately but not for several issues
Hi all. I've got a problem with Jira calculating the control chart. My goal - find out the cycle time and have a breakdown for each status. I've got three of them (To Do, Dev&QA, UAT) and s...
Hi, We have recently noticed that the control chart showing wrong data, in several projects. All of them occurring during the month of June. However, the Transitions section of the issue s...
I have three columns set up in my board (To Do, In Prog, Done). In my workflow, there are 5 states (Captured, Ready, In Prog, Done, Accepted). The mapping between the columns and workflow state is as...
How is the "Average" time calculated on a Control Chart? More specifically, I see one of my average cycle times is "1w 1d 5h" but then another one is "6d 3h"..... I do NOT have "Include non-working d...
I have a project on a Kanban board using a Simplified Workflow with columns appropriately mapped to "To Do," "In Progress," and "Done." Whenever I go to my Control Chart, all stories that are "Done" ...
Hi, Big fan of the JIRA control chart, but it is not terrible clear if cycle time is including non working hours. How can the Control chart be configured to only record cycle time during working hou...
Morning, First of all comment that my English is very bad, cause I'm Catalan and I don't speak usualy english. I try to do understand me you. Thank's Someone knows How I can add parameters in the C...
The question is - how does Control Chart works in details. Preconditions - for instance we have Kanban dashboard with 3 columns - Open, In Progress, In Testing. we have following config...
I am using a scrum board and have the following columns set up with the following statuses for when you view the active sprint. Ready Dev WIP&nbs...
Hi, In our global time tracking settings we have Working hours per day - 8 Working days per week - 5 In the control chart for a sprint board I see the following values: - Without including...
I run a cycle time report at the end of every month for one of my teams. I have 4 categories: To Do (open), In Progress (in progress), Ready for Release (resolved), and Closed (closed). I ...