Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,558,949
Community Members
 
Community Events
184
Community Groups

make due date of new card dependent on due date or custom field date of another card

How can I create an automation whereby each new card I create in a certain list gets a due date dependent on the due date (or custom field date) of an existing card? Is that even possible? It's in itself a very simple formula, but I don't know how to get it to work in automations.

For example:

List = issue 5.4 magazine

Card 1 = Press date (this due date or custom date field will determine all the following cards)

Card 2 = Edit close (press date -60 days)

Card 3 = Ad close (press date -30 days)

Etc. 

 

All suggestions welcome! Thanks

1 answer

0 votes
Hannah Morgan
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
Sep 07, 2022

Hi @Katinka Domen ! Welcome to the community :) I created a quick video a while ago showcasing a similar workflow. Basically, the idea is you set a date on a card (like a project or milestone due date), and this then determines the dates on the dependent or related cards.

https://www.loom.com/share/d6347f1b1f0a4e7fae41f5981d856538

In your case, you would be subtracting days from the date rather than adding.

Hi Hannah.

 

This only works if all intervals are the same though, right? If for example I wanted to do something like this:

 

Project date: 25 nov

First linked card: project date -10days

Second linked card: project date -20days

Third linked card: project date - 50days

 

Is that possible too?