Butler automation: setting due dates on linked cards converted from check-items

Hello! I'm wanting to automate setting a due date on a linked card. 

This is what I've created so far and it's working fine:
When a check-item is added to checklist "X", convert the check-item into a linked card, copy the labels, and move it to board "X"


-->What I'm looking to achieve is to automatically set a due date on the linked card. 


Ideal scenario:
Copy the due date from the parent card to the linked card and move it by "X" amount of days.

Bonus:
If the due date on the parent card changes, this should cause a cascading effect and update the due date by the same amount of time on the linked cards.


Is this possible, or is there another way to achieve this so I'm able to automatically set the due dates on the linked cards? Open to other suggestions!

Thank you! :)  

2 answers

2 accepted

0 votes
Answer accepted

@Hannah 

If you are using only Butler, the first hurdle will be to use the date like a card due date to set the due date for another card. 
In my reply in this post https://community.atlassian.com/t5/Trello-questions/Automated-planning-for-a-project/qaq-p/1749777#M49227

I shared a piece of work that allows for dates to be set on a set of items and or it’s linked subtask cards. The date input can be a start date or a deadline. Without the use of a custom field override it will be fixed days between items or card otherwise it will take a set of comma delimited numbers and apply to the checklist. 

@Hannah 

This video is before I added the override. 
https://youtu.be/6nSRM6WmDdI

@Hannah 

This implementation is more generic and it is intended to be used from within Butler

https://trello.com/c/h9QvOF0R

@Hannah 

It is always good to learn a new way to do it.

Update : change pattern to {newcardlink}

Lastly :

when a due date is set on a card, for each card linked from an item in checklist "Checklist A", rename the card to "{multipliercardname} {triggercardduedate}"

Screen Shot 2021-07-21 at 9.27.22 AM.jpg

Great - thank you! I'll take a look into it

0 votes
Answer accepted
Iain Dooley Community Leader Jul 20, 2021

@Hannah I think what you can do is add a label to the "parent" that will copy to the linked card, then have a separate rule triggering when a card is created with that label on it to look for the due date  on the first card linked in the attachments, get the due date and set it on the trigger card.

The only trigger is that you'll need to first set the due date on a custom field in the trigger card then set the date to the date in the custom field (an unfortunate little workaround because there's no way to directly set one card's due date based on another card's due date)

Thanks, Iain! I'll do some digging.

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Published in Trello

🏊‍♀️ Atlympic Event: Trello

Hello Community!  Quick disclaimer: We are running a contest on Community (The Atlympics!) from July 23rd - August 8th of 2021. If you are interested in participating in this contest (prizes! ...

181 views 2 13
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you