See sub-tasks added after sprint started

I'd like to see sub-tasks created on a stories within a sprint, so we can see what wasn't really thought of as part of sprint planning. I could take this information in to a retrospective to discuss.

1 answer

1 accepted

GreenHopper doesn't really differentiate sub-tasks added before and after sprint started. In Plan mode, sub-tasks can not be added to a sprint independently of their parent. Adding sub-tasks to issues already in a sprint is not considered a scope change. However you can try and use JQL to query all subtasks that are in an active sprint and that are created after the sprint start date. Something like:

project = "My project" and sprint = "Sprint 9" and issuetype = SubTask and Created >= "2013/06/01"

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Published Thursday in Marketplace Apps

Tips on how to choose the best estimation method for your planning

Planning and grooming sessions all come with their own sets of rules. Team members meet to estimate stories or other work items, all according to an agreed-upon process. And with every session comes ...

75 views 0 11
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you