Hi, I created a group "Developer", and add 2 user in the group. Then there are 2 developer in a project. I try to assign an issue to 1 developer, but I don't know why another developer can click "start progress" and get the assignee. How can I make the issue can only be "start progress" by assginee.

Thanks.

1 answer

Hi,

You need to restrict your "start progress" transition in your workflow to be available to the assignee only.

1. Open up your workflow in edit mode and locate your transition "start progress"

2. Select View Conditions

3. Add a new condition

4. Select Only Assignee Condition and click Add

5. Publish your updated draft workflow

Now only the assignee will be able to start the progress of the issue!

Hope this helped!

Rgrds,

// Svante

It works. Thank you very much~!

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Published in Jira Align

Best Practices in Jira Align

Hello Jira Align customers! In order to better serve you on your journey with Jira Align, the Community team has worked with the Jira Align team to curate the content in this collection to better s...

44 views 0 2
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you