Burndown chart does not process removed hours from sprint

Kevin
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
October 6, 2014

Due to several reasons I had to replace some tasks with new tasks from the backlog, while the sprint was already started.

The tasks I had to remove were estimated at 40h and the tasks I've put into the sprint are 40h as well. According to my calculations there should be a drop in the 'remaining hours' line in the burndown chart when I remove the tasks and it should go right up again when I add the new tasks to the sprint, making it show the initial amount of remaining hours as before I swapped the tasks.

Unfortunately, the burndown chart only shows the hours that are added, without removing the hours of the tasks that have been removed from the sprint.

How come? Is there any way I can prevent this from happening? In my opinion the burndown chart is not accurate anymore. See below.

Schermafbeelding 2014-10-07 om 14.11.40.png

1 answer

0 votes
Kevin
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
October 27, 2014

Anyone has an answer?

Suggest an answer

Log in or Sign up to answer