helo everyone, i have problem with jira report. i estimate for task in sprint. but when i running sprint, i can't see a burndown report. please help me urgent !
Welcome to the Atlassian Community!
Assuming it is a Company-managed scrum or kanban
1> we using subtask, it not working for burndown and burnup chart, right?
2> we will hide task when done in last column, it mean all task in close sprint will not show in active sprint. so velocity can't show it, right?
1. Burndown is a function of sprints. Sub tasks (in Jira) are part of a story, not sprint items. So sprint estimation on sub tasks is nonsense. Do not do it (other estimation is fine, just not sprint/scrum)
2. If you hide it, then by definition, you cannot report on it.
Help you with what? We've already explained what you're doing that needs to change.
Recommended Learning For You
Level up your skills with Atlassian learning
Learning Path
Get started with Jira Software
New to Jira Software? These short, self-paced courses will teach you what you need to know to get up and running quickly.
The Beginner's Guide to Agile in Jira
Learn what agile, kanban, and scrum are and how agile works in Jira Software.
Realizing the Power of Jira Reporting and Dashboards
Use out-of-the box reporting and dashboard capabilities to view and assess progress and bottlenecks within projects.