In a Business project, the core boards of To Do, In Progress, and Done- I'd like to change the default to show longer than 14 days of Done items-- any idea where, or if, this is configurable?
Thanks!
Go To: Board >> Configuration >> General
At the bottom there is a drop down as; "Hide completed issues older than"
Default value is 2 weeks, set it to `Show All`
Thanks for this-- but is this for on-prem solutions? We're cloud, and don't see 'COnfiguration' as a choice in Board. (yes, I'm an admin for the whole system.)
Thank you for your response!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This feature was released in 7.9.x: https://confluence.atlassian.com/jirasoftware/jira-software-7-9-x-release-notes-946034808.html
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.