is there a checklist to verify that JIRA is fully functional after an upgrade?

George Keratiotis
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
May 23, 2016

Hello,

We are planning an upgrade of our JIRA server and we need a check-list of test cases to execute in order to verify that the upgrade is successful. Is there one you have or can propose?

Thanks.

 

G.

 

1 answer

0 votes
Jonas Andersson
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
May 24, 2016

Not that i am aware of but i tend to check this:

Before upgrade

  • Does all plugins exist in my destination version?
  • Read all release notes from current to destination version, make sure no functionality you rely on is changed. Same for critical plugins

After upgrade

  • Can i still login? (we use AD)
  • Does ldap still sync?
  • Does application links/activity streams still work?
  • Go through the list of all plugins. Are they all updated the latest version?
  • Check all plugins you deem as critical, simple functional tests for very important stuff
  • Does attachments/profile pictures still work?
  • Is still all tomcat settings correct? Verify all http/https ports you expect to be open. Check that the keystores are not replace by listing all certificates.

 