I just upgraded to Jira 5.0.2 (from 5.0.1).
In the plugin manager, it says UPM needs an upgrade, but it does not upgrade.
It keeps saying: Preparing to update UPM... but never finishes.
I found this in catalina.out:
2012-04-03 16:22:33,821 QuartzWorker-1 ERROR ServiceRunner upmPluginUpgradeCheckJob [sal.jira.scheduling.JiraPluginSchedulerService] Unable to load a service descriptor for the job 'upmPluginUpgradeCheckJob'. This is usually the result of an obsolete service that can removed in the Administration section.
Same problem here, during am upgrade from Confluence 3.5.6 to 4.1.9. Had to install the new version by hand.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
How to update a plugin manually:
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
If you are using UPM 2.7.8 or 2.7.9, you are probably facing the problem described in this KB:
UPM Self-Update fails when updating from UPM 2.7.8 or 2.7.9 to newer versions
Basically, you will need to manually upgrade your UPM plugin in JIRA by following this documentation.
Cheers,
Andre
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.