compare original effort with time spent

I tried to compare in a filter the original effort with the time spent and JIRA claimed that this is an invalid comparison (The value 'timespent' for field 'originalEstimate' is invalid) . I would like to figure out all tasks which took longer than the estimate this way. Any thoughts?

2 answers

1 accepted

8 votes
Answer accepted

Hi René,

Try JQL language & the Keyword "workratio" (available on my jira 4.4.4). I use it to identify jira where I spent more time than expected. ("workratio >100").

Hope this help.

Steph from France

Hi, "workratio" do not take account the original estimate & time spent in sub-tasks :( 

Like Mathieu Duczmanski likes this

If you want to read more on the topic:

https://confluence.atlassian.com/display/JIRA/Advanced+Searching

WorkRatio is calculated as follows: workRatio = timeSpent / originalEstimate) x 100

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted in Jira

Demo Den Ep. 7: New Jira Cloud Reports

Learn how to use two new reports for next-gen projects in Jira Cloud:  Cumulative flow diagram and Sprint burndown chart. Ivan Teong, Product Manager, Jira Software, demos the Cumulative ...

334 views 1 3
Join discussion

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you