i have 100 backlogs in my project and i would like to know the total story points for the backlogs i have. is there any other way aside from creating a sprint and adding those backlogs one by one in it? tia
That's not currently a feature. There's a workaround with code here: https://answers.atlassian.com/questions/162183
The feature has been requested, but it doesn't look like it will be implemented soon
https://jira.atlassian.com/browse/JSW-3676
You could always export your issues to Excel and sum up the Story Points, but that's not much better than the sprint workaround you use.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You're welcome
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.