Why can blocked issues be completed?

Chris_이기훈_ August 3, 2020

Among the issues linked by issue linking, the blocked issue was not resolved, but why is it possible to complete the process?

1 answer

1 accepted

0 votes
Answer accepted
Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
August 3, 2020

You are making an incorrect assumption.  Just because an issue has a link to another, with a name like "blocked by" does not mean Jira knows that you want to prevent progress on it.

If you want it to do that, you can, you will need to edit the workflow, adding conditions to it that prevent people using any "close issue" type transitions.

Chris_이기훈_ August 3, 2020

Thank you for your answer.