When doing an external import via CSV, I can't import to the "Active Sprint" field

I am working on doing an import of user stories and tasks from Target Process. I cannot see a way to map my "Iteration" to the Agile Field "Active Sprint" I could do a custom field, but it's unclear what the data type should be and how this will interact after the import.

I am using the GreenHopper plugin.

1 answer

0 votes
Renjith Pillai Community Champion Aug 27, 2012

If you are talking about Sprints in Rapidboard, it is stored in a custom field by the name 'Sprint'. But changing that directly is not recommended as this will lead the Sprint history of GreenHopper inconsistent.

If you are looking at the usage of Classic boards, then the sprint information is stored in Fix Version(s) and the CSV import wizard directly supports this.

So there's no way to import to import such that greenhopper sees it?

Suggest an answer

Log in or Join to answer
Community showcase
Sarah Schuster
Posted Jan 29, 2018 in Jira

What are common themes you've seen across successful & failed Jira Software implementations?

Hey everyone! My name is Sarah Schuster, and I'm a Customer Success Manager in Atlassian specializing in Jira Software Cloud. Over the next few weeks I will be posting discussion topics (8 total) to ...

2,798 views 11 18
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot