A few teams and I have been ordered to use new Versions to show version containers. So to do this accurately we had to move completed stories that were not in a version; or stories that were attached to other versions into the version.
1) I edited stories, etc to have the Fixed Version be the Version Name I desire
2) Migrated the other versions into the new Version Name
In the end, the version report basically shows nothing from Feb 19 to April 30 (today) in the brundown, and show everything on April 30 as a delta change. So, the burndown only works from today and no longer shows a history.
Is there any way to fix this?