I was not able to find a possibility in GreenHopper to show me the calculated velocity over the last X sprints.
Currently we do this manually: we add together the story points of the last 3 sprints and divide the result through 3 (sprints).
Is this also possible with GreenHopper? If not would it be possible to add this as a feature in the upcomming versions?
This can be done using the Agile gadget which has a velocity tab, you will have to select each sprint from the dropdown in turn.
Alternatively if you have it setup so you have a "Feature backlog" as the parent of all issues then when looking at the statistics burn down chart for story points you will see an option under daily called children which opens up a histogram of your velocity burndown sprint by sprint.