Using JIRA Portfolio

Hi,

When I import epics into the portfolio manager it is not bringing over the stories and tasks already associated and linked to that epic. Is that the way the epic import is suppose to work or is something wrong? What is the best was to go about this?

 

Thanks!

 

1 answer

0 vote

Hello Kristen,

        The import is not supposed to work this way.

        Actually you will need to select all the stories you want to import.

        To make your job easier you could create a filter in JIRA, save it and use this filter at the Portfolio import. This could enable you to easily select the issues you want to import.

        This is the import documentation as reference: https://confluence.atlassian.com/jiraportfoliocloud/adding-existing-issues-to-your-plan-715263473.html

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Published yesterday in Jira Software

How large do you think Jira Software can grow?

Hi Atlassian Community! My name is Shana, and I’m on the Jira Software team. One of the many reasons this Community exists is to connect you to others on similar product journeys or with comparabl...

193 views 4 8
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you