Unable to see child issues on timeline.

Aaryan Bansal
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
March 17, 2024

I have enabled child-level issue scheduling on timelines and set due dates for all issues but I am still unable to see issues other than epics on my timeline. 

 

Screenshot 2024-03-18 at 4.33.06 pm.png

2 answers

0 votes
Walter Buggenhout
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
March 30, 2024

Hi @Aaryan Bansal and welcome to the Community!

Navigate to your board settings / timeline and make sure you enable the child level issue scheduling option. After that, you should be able to add timeline bars to these child issues as well.

Hope this helps!

0 votes
Mohanraj Thangamuthu
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
March 17, 2024

Hello, Good day. Parent issue should be on Epic issue type level, then the issue will be shown on Timeline. Please check the requirement : https://support.atlassian.com/jira-software-cloud/docs/set-up-the-roadmap/

Aaryan Bansal
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
March 17, 2024

All the issues are child issues on my epic. 

 

Screenshot 2024-03-18 at 5.45.27 pm.png

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
FREE
PERMISSIONS LEVEL
Product Admin
TAGS
AUG Leaders

Atlassian Community Events