My team has started using Tempo timesheets to log time. As team lead/program manager I would like to forecast future resourcing needs by planning time for each team member. I don't want the team members to see the planned time, as this will just be confusing and useless information for them.
Right now the planned time shows up in the My Work calendar view for each user and I haven't been able to modify permissions or options to hide the planned time. Is this possible?
Thanks
Hi @Julie Chiappari ,
It is not possible to hide the plans made for a user in the My Work view.
This view is used to make sure that users are aware what work has been planned for them ( what are they supposed to work on) and to create their own plans.
It is only possible to restrict the visibility of plans made for other users ( using the "View plans permission" for the team).
Regards,
Susanne Götz
Tempo team
Thank you for your reply, now I can stop looking for this setting.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Are there any plans to add this feature? It would be so crucially helpful for me.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Same here, I will find this feature helpful too in resource planning for my team
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.