I have the following statuses. All other statuses exept done will be shown, but not done. If I move the task to in progress and the to done, it will show, but after a while thei will disapear. Is there some kind of time limit for done issues?

 

image.png

1 answer

1 vote
Jack Brickey
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
June 11, 2024

Hi @Martin Vali , you mention "done" status but I don't see it on the board. I do see three statuses of statuscategory = done. Maybe you are saying that issues move to any one of those there columns disappear? 

  • is this a TMP or CMP project (look in bottom left)
  • if CMP please share your board filter and sub-filters from board config General page
  • If CMP please share an image of your Columns page
Trudy Claspill
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
June 11, 2024

Adding to this...

If you are working with a Team Managed Software project, issues moved to the column farthest to the right will automatically be hidden when they have been in that column for 2 weeks or longer.

If you are working with a Business (aka Work Management) project, regardless of whether it is Team Managed or Company Managed, issues set to any green colored status will be hidden when they have been in that status for 2 weeks or longer.

These are non-configurable, hard coded functionality in these types of project boards.

You can find the project Type information in the Type column on the View All Projects page under the Projects menu.

Only in Company Managed Software projects where you use a Kanban board can the hiding of "done" issues be configured.

Like Jack Brickey likes this
Martin Vali June 12, 2024

Hi,

Yes, I meant statuscategory done and yes they dissapear there after a while - dunno currently the time

This is CMP business

Board filter

Screenshot 2024-06-12 123512.png

Where can I find sub filters and board config General page?

By Column page you mean board page?

in Screenshot 2024-06-12 124701.png

In list view I can see them

Screenshot 2024-06-12 125115.png

Martin Vali June 12, 2024

@Trudy Claspillso if I understood correctly, this is normal that in business project they disapear and can not be changed?

Martin Vali June 12, 2024

So to see my active clients I changed the Active from Done category to in progress

Screenshot 2024-06-12 130001.png

Trudy Claspill
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
June 12, 2024

@Martin Vali 

Yes, this is by design for a Business project.

There is a change request to allow this to be configured. I don't have the request ID handy, but I'll find it and add it here later.

Like Jack Brickey likes this
Jack Brickey
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
June 13, 2024

Thanks @Trudy Claspill ! I have been slammed with works and life this week and consequently away from the Community. It looks like you have zeroed in on the cause here.this may be the issue of interest - https://jira.atlassian.com/browse/JWMCLOUD-19 . You will note that a recent update from Atlassian PM indicates no immediate plans to take this on.

Like Trudy Claspill likes this

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
FREE
PERMISSIONS LEVEL
Product Admin
TAGS
AUG Leaders

Atlassian Community Events