Your workflow for sub-tasks is incorrect, OR your column mappings are incorrect.
Have a look at the board config first - what status are in the "done" column?
Now look at the workflow for each type of sub-task in the project - at least one of them will not have any status that you noted were in the "done" column.
Cheers Mate!
For some reason board creation failed.
So actually I did not have a board for this project to support the sprint :|
I re-created the board and voila... things are working again.