Some future sprints have an end date automatically set. Where does JIRA take this info from?

arama mihai
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 2, 2018

Hello,

We noticed that for some future sprints, not all, an end date is automatically set in the agile side panel.

I added an attachment so that it's more clear to what I'm referring.

I also entered JIRA in safe mode and it was still appearing, so I assume it's not from an add-on.

Where does that date come from?

Thank you!

 

sprint end date.png

1 answer

0 votes
arama mihai
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 2, 2018

The date is added by the Big Picture add-on when a program has a synchronization for JIRA Agile Sprints set, and the end date on the gantt chart is brought to the JIRA issue.