Set an estimation for sub-issues

Hi all,

i am new with JIRA administration. Former I was using it as a developer.

Our Plan:
1. everybody defines issues
2. issues get separated in subissues
3. our projekt adminstrator plans our sprints by issues which have an estimation.

our Problem:
Subissues cannot get an estimation...
Is there any way to setup an estimation?

Regards

 

2 answers

Sub-tasks can get an original estimate on them, if you add the time tracking fields to the screens corresponding to sub-tasks. and you can add time estimates by editing the sub-task.

However, if you are using jira-agile then it is a different story altogether. 

Go through these links to familiarise yourself to the concepts of adding fields to screens

https://confluence.atlassian.com/display/JIRA/Configuring+Fields+and+Screens

https://confluence.atlassian.com/display/JIRA/Associating+a+Screen+with+an+Issue+Operation

https://confluence.atlassian.com/display/JIRA/Defining+a+Screen

Pilar

We use JIRA on *.atlassian.net. Could not even find the option mentioned in the second of your links

"Choose > Issues. Select Screens > Screen Schemes"

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Nov 27, 2018 in Portfolio for Jira

Introducing a new planning experience in Portfolio for Jira (Server/DC)

In the past, Portfolio for Jira required a high degree of detail–foresight that was unrealistic for many businesses to   have–in   order to produce a reliable long-term roadmap. We're tur...

2,299 views 12 19
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you