We are managing our Agile Portfolio in Advanced Plans and are struggeling to find a handling to roll up Storypoints from Sprints (2w) to Product Increments (12w).
Example Setup Daterange 01.01.2025 - 31.03.2025
BI-Weekly Sprints
Sprint 2025/1-1, Sprint 2025/1-2
Sprint 2025/2-1, Sprint 2025/2-1
Sprint 2025/3-1, Sprint 2025/3-2
PI-Sprint
PI-Sprint 2025-1
The BI-Weekly Sprints only contain workitems like Tasks, Userstories etc., the PI-Sprint only Epics. All workitems are assigned to a parent-Epic.
I can see the storypoints per epic and team rolled up in the advanced plans, but they do not show up in the planed point in the PI-Sprint. But when an workitem is set to done, the storypoint value gets included in the PI-Sprint when I include the bi-weekly sprint in the plans view.
Therefore my question:
Is there a way to include the rollup value for storypoints (all status) in the sprint of the parent issue?