If I have a task that lasts N days and I have a resource who will only be allocated to that task for a percentage of the N days. i.e. a Testing Task that we schedule will take 40 days may require some support from a development resource to answer queries. I have make a provision for the developers time as I don't know how much will actually be required. I want to allocate them for 10% of their time over the 40 days to ensure I have a budget for them. I may not need time from them every one of the 40 days but some days they will do a few hours work supporting the project.
How do I situation up in JIRA/Tempo? Thanks