Jira agile sprint finalization

This question is in reference to Atlassian Documentation: Configuring sub-tasks

I'm using a another status for subtasks named 'Failed'.

I mapped the status on the workflow to the 'Done' category.

Now, when I try to complete a sprint and there is a story (in Done status) that has a subtask in 'Failed', Jira will not let me complete the sprint claiming that there are incomplete subtasks in it.

Am i missing something or is Jira Agile looking for the explicit 'Done' status of subtasks ?

1 answer

1 accepted

Accepted Answer
0 votes

The exact status isn't too important, and nor is the status category.

Try reconfiguring the board, putting the "failed" status into the far-right hand column on the board.

Thanks !!!, works.

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Tuesday in Jira

Looking for anyone who made the switch to Data Center

The Jira Marketing team is putting together an ebook on migrating to Data Center. We're looking for pro tips on how you staffed your project team and organized your Proof of Concept. Share yo...

36 views 0 2
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you