JIRA Portfolio timeline starts at a very old date

Hi

I setup my live plan based on a couple of boards. After the wizzard is completed, portfolio shows the timeline (see picture). Problem: The start date is too old. That leads to a situation where a lot of the timeline space is empty. Why is that? I only work with new releases, epics don't seem to have an old start date etc.

Thanks,

Erwin

Portfolio.jpg

1 answer

I found the reason. Somewhere in a board I had an orphan sprint from the specific old date. Portfolio works as expected.

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Sep 25, 2018 in Jira

Atlassian Research Workshop opportunity on Sep. 28th in Austin, TX

We're looking for participants for a workshop at Atlassian! We need Jira admins who have interesting custom workflows, issue views, or boards. Think you have a story to sha...

433 views 7 5
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you