JIRA: I've put a sprint in the wrong week, how can I reverse this and put into the correct week

hello

 

I completed a sprint for last week and have to move it to this week, unfortunately I pressed the wrong date and its now for next week instead. How do I make the sprint for this week please?

1 answer

Hi Lisa,

 

Take a look here :

https://confluence.atlassian.com/jirakb/how-to-edit-the-dates-associated-with-a-closed-sprint-779159174.html

This require you have access to your jira database. Do you have this access?

 

Hope this help.

 

Best regards,

Christophe

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Tuesday in Jira

What modern development practices are at the heart of how your team delivers software?

Hey Community mates! Claire here from the Software Product Marketing team. We all know software development changes rapidly, and it's often tough to keep up. But from our research, we've found the h...

241 views 1 3
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you