In portfolio, is there a way to plan with team velocity increasing over time?

I'm using portfolio for our Roadmap which meant that the scope I'm playing with covers multiples years.

I would like to know if this is possible to have the team velocity increase over time ... let say, 10% each year.

 

1 answer

0 votes

Hi @Nicolas Gendron,

 

This is currently not supported directly but as a workaround if you are using time planing I'd suggest having a look at exceptions which allow to define a team member weekly capacity over a specific period of time.

 

Also I've created a feature suggestion for Portfolio for Jira server here: JPOSERVER-2044

 

Cheers,

Thomas.

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Feb 13, 2019 in Jira

Make your Atlassian Cloud products more secure: our NEW admin security guide

Hey admins! I’m Dave, Principal Product Manager here at Atlassian working on our cloud platform and security products. Cloud security is a moving target. As you adopt more products, employees consta...

599 views 0 12
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you